块石戗堤先行进占施工的土石围堰稳定性研究

Research on the Stability of Earth-rock Cofferdam Constructed by the Method of the Rock Dike Filling Ahead

  • 摘要: 对于内侧采用含砾黏土、外侧采用块石戗堤的土石围堰结构,为研究其进占方法对围堰稳定性的影响,以邕宁水利枢纽一期枯水土石围堰为工程背景,首先提出了"块石戗堤先行,含砾黏土跟进"的施工方案,根据块石及含砾黏土边坡和跟进距离的几何关系确定了含砾黏土侵入距离的计算公式;其次,基于流固耦合理论,研究了不同基坑排水速度时,渗流场和应力场耦合作用下围堰的工作状态,利用有限元分析软件ABAQUS结合有限元强度折减法,对含砾黏土侵入块石戗堤底部时形成的围堰进行了计算,分析了围堰的整体变形、剪切破坏及失稳特征。结果表明:随折减系数增大,塑性区从外侧堰底开始发育并逐渐形成贯通区,最大变形值出现在外侧堰底;含砾黏土跟进距离大于等于临界值16.22 m时,跟进距离的选取对堰坡稳定性的影响较小,而跟进距离小于16.22 m时,含砾黏土侵入块石戗堤底部数量过多,导致外侧堰体抗滑稳定承载力下降,围堰稳定性受到威胁。为保证围堰的安全稳定,建议将含砾黏土跟进距离控制在17 m左右。

     

    Abstract: In order to study the influence of filling method on the stability of cofferdam which has grain-containing clay on the inside and block stone on the outside based on the 1 st earth-rock cofferdam of Yongning Water Conservancy Project,this paper firstly proposes the filling method of"block stone dike first,grain-containing clay follow-up"and determines the formula for calculating the intrusion distance of grain-containing clay according to the geometric relationship between the slope of block stone and the grain-containing clay and the followup distance. Secondly,based on the fluid-solid coupling theory,it studies the cofferdam working state influenced by seepage field and stress field under different drainage velocity of the foundation pit and combined ABAQUS with finite element strength reduction method to calculate the cofferdam in which grain-containing clay has intruded to the bottom of the dike. The results show that with the increase in reduction coefficients,the plastic zone develops from the bottom of the outside and gradually forms a penetrating plastic zone,and the maximum deformation appears at the bottom of the outside. The stability of the cofferdam is less influenced by the follow-up distance of grain-containing clay when it is more than or equal to the critical value of 16.22 m.When the follow-up distance is less than 16.22 m,the amount of grain-containing clay intrusion into the bottom of the dike is too large,which leads to the decrease in the bearing capacity of the cofferdam,and the stability of the cofferdam is threatened. In order to ensure the safety and stability of the cofferdam,it is recommended to control the follow-up distance of the grain-containing clay to be around 17 m.

     

/

返回文章
返回